To edit a resource requirement:
- Click the resource type cell in the time period you want to edit and type the number of hours (or FTE value) desired for that period. A blue border will appear around the specific cell that is being edited.
Note: the value entered into a requirement must be positive. The maximum number allowed for FTE entries is 99.99. The maximum number allowed in Hour mode is 15,840.99.
- Repeat step 1 for each requirement you want to edit. You may edit multiple requirements before saving.
- Once all the values have been updated appropriately, click Save at the top of the Resource Plan to commit the changes to the system.
As the requirements are edited, the “Remaining” value beneath the requirement will be updated automatically. This value represents the difference between the Requirement and the total for all resource allocations for the requirement for the given time period.